Construction Updates
Williams/Ledger Elementary School Reconstruction
The reconstruction of Williams/Ledger Elementary School follows substantial damage to the campus which occurred during heavy rains in July 2025. This project was declared an emergency by the CCISD Board of Trustees at its Aug. 12, 2025 meeting and is being funded through fund balance and the district's insurance provider.
Nov. 17, 2025
Dec. 5, 2025
Dec 17, 2025
Jan. 7, 2026
Jan. 21, 2026
Feb. 9, 2026
Feb. 13, 2026
Feb. 27, 2026
March 25, 2026
April 15, 2026
June 2, 2026
Aug. 3, 2026
Elementary School Playground Replacement
On December 15, 2025, the Copperas Cove ISD Board of Trustees approved the replacement of playgrounds at all five K-5 elementary campuses in Copperas Cove ISD, with each including a shade to meet modern student safety standards. These projects total $2,693,185.68 and will be paid for out of Fund Balance.
These projects are on track to be completed ahead of the 2026-27 school year.
Renderings
April 30, 2026 - MWE
April 30, 2026 - HHE
May 13, 2026 - MWE
June 3, 2026 - CPE
June 3, 2026 - HCE
June 3, 2026 - HHE
July 27, 2026 - HCE
August 10, 2026 - MWE
August 12, 2026 - HHE
August 13, 2026 - HCE
August 13, 2026 - WLE
Bulldawg Stadium Track Resurfacing
The Board of Trustees approved the resurfacing and repair of the track at Bulldawg Stadium at their February 3, 2026 regular meeting at a cost of $415,700.00 from fund balance. After the track was removed following the conclusion of the Track & Field Season, additional repairs to the asphalt underneath the track. Those additional repairs were approved by the Board of Trustees on April 27, 2026 at a cost of $180,170.00 from fund balance. Both portions of the project are being completed by ProTech Track & Tennis and the project is projected to be complete in the Summer of 2026.
April 16, 2026
April 24, 2026
May 22, 2026
June 4, 2026
June 24, 2026
Outdoor Venue Lighting
The lighting at outdoor venues across Copperas Cove ISD sustained damage during hail storms and was not working to an effective level. The replacement of the existing lighting at all outdoor facilities with LED lighting was approved by the Board of Trustees on May 12, 2026, with Symmetry Sports Construction for a total cost of $707,250.00. The district is working to recover the money from its insurance company, with the contract approved pay out of fund balance.
Before
May 22, 2026 - Bulldawg Stadium
May 26, 2026 - Bulldawg Stadium
May 27, 2026 - Bulldawg Stadium
May 27, 2026 - Hanke Field
June 2, 2026 - Hanke Field
June 2, 2026 - CCHS Tennis Courts
Hanke Field Track Replacement
The Board of Trustees approved the resurfacing and repair of the track at Hanke Field, located at S.C. Lee Jr. High, at their March 23, 2026 regular meeting at a cost of $297,904 from fund balance. The project is being completed by ProTech Track & Tennis and the project is projected to be complete in time for the 2026-27 school year.
Before
Completed Projects
Lea Ledger Auditorium Rigging Update - Completed January 2026
Photos
Baseball & Softball Field Conversion - Completed January 2026
Photos
Crossroads High School Soft Scrubbing - Completed February 2026