Construction Updates
Ongoing Projects
Copperas Cove Jr. High School Renovation
Renderings
Asbestos Abatement - Sept. 10, 2026
Demolition Begins - October 5, 2026
LED Lighting Upgrades
August 12, 2026 - Hettie Halstead Elementary
September 23, 2026 - Hettie Halstead Elementary
September 23, 2026 - Mae Stevens Early Learning Academy
October 6, 2026 - S.C. Lee Jr. High School
Elementary School Playground Replacement
On December 15, 2025, the Copperas Cove ISD Board of Trustees approved the replacement of playgrounds at all five K-5 elementary campuses in Copperas Cove ISD, with each including a shade to meet modern student safety standards. These projects total $2,693,185.68 and will be paid for out of Fund Balance.
These projects are on track to be completed ahead of the 2026-27 school year.
Renderings
April 30, 2026 - Martin Walker Elementary
April 30, 2026 - Hettie Halstead Elementary
May 13, 2026 - Martin Walker Elementary
June 3, 2026 - Clements/Parsons Elementary
June 3, 2026 - House Creek Elementary
June 3, 2026 - Hettie Halstead Elementary
July 27, 2026 - House Creek Elementary
August 10, 2026 - Martin Walker Elementary
August 12, 2026 - Hettie Halstead Elementary
August 13, 2026 - House Creek Elementary
August 13, 2026 - Williams/Ledger Elementary
August 17, 2026 - Fairview/Jewell Elementary
September 23, 2026 - Fairview/Jewell Elementary
September 23, 2026 - Hettie Halstead Elementary
Completed Projects
Hanke Field Track Replacement
The Board of Trustees approved the resurfacing and repair of the track at Hanke Field, located at S.C. Lee Jr. High, at their March 23, 2026 regular meeting at a cost of $297,904 from fund balance. The project is being completed by ProTech Track & Tennis and the project is projected to be complete in time for the 2026-27 school year.
Before
August 13, 2026
September 21, 2026
Bulldawg Stadium Track Resurfacing
The Board of Trustees approved the resurfacing and repair of the track at Bulldawg Stadium at their February 3, 2026 regular meeting at a cost of $415,700.00 from fund balance. After the track was removed following the conclusion of the Track & Field Season, additional repairs to the asphalt underneath the track. Those additional repairs were approved by the Board of Trustees on April 27, 2026 at a cost of $180,170.00 from fund balance. Once the asphalt was removed, additional repairs were found to be necessary. Concrete Stabilization was approved by the trustees at a cost of $89,866.00 at a Special Called Meeting on May 11, 2026. The project was completed in July 2026.
April 16, 2026
April 24, 2026
May 22, 2026
June 4, 2026
June 24, 2026
Outdoor Venue Lighting
The lighting at outdoor venues across Copperas Cove ISD sustained damage during hail storms and was not working to an effective level. The replacement of the existing lighting at all outdoor facilities with LED lighting was approved by the Board of Trustees on May 12, 2026, with Symmetry Sports Construction for a total cost of $707,250.00. The district is working to recover the money from its insurance company, with the contract approved pay out of fund balance.
Before
May 22, 2026 - Bulldawg Stadium
May 26, 2026 - Bulldawg Stadium
May 27, 2026 - Bulldawg Stadium
May 27, 2026 - Hanke Field
June 2, 2026 - Hanke Field
June 2, 2026 - CCHS Tennis Courts
Williams/Ledger Elementary School Reconstruction
The reconstruction of Williams/Ledger Elementary School follows substantial damage to the campus which occurred during heavy rains in July 2025. This project was declared an emergency by the CCISD Board of Trustees at its Aug. 12, 2025 meeting and is being funded through fund balance and the district's insurance provider.
Nov. 17, 2025
Dec. 5, 2025
Dec 17, 2025
Jan. 7, 2026
Jan. 21, 2026
Feb. 9, 2026
Feb. 13, 2026
Feb. 27, 2026
March 25, 2026
April 15, 2026
June 2, 2026
Aug. 3, 2026
Lea Ledger Auditorium Rigging Update - Completed January 2026
The update to the rigging system at Lea Ledger auditorium, including the control system used for operating the rigging, was approved by the Board of Trustees at its Nov. 19, 2024 meeting and paid for out of fund balance.
This project was completed in January 2026.
Photos
Baseball & Softball Field Conversion - Completed January 2026
The conversions of the Copperas Cove High School baseball & softball fields to artificial turf was approved by the Board of Trustees at its Aug. 12, 2025 meeting and paid for out of fund balance.
Both fields are on track to be completed in time for practice to begin in January 2026.
Photos
Crossroads High School Soft Scrubbing - Completed February 2026